Attached files

file filename
EX-23.4 - EXHIBIT 23.4 - NIOCORP DEVELOPMENTS LTDv448164_ex23-4.htm
EX-23.2 - EXHIBIT 23.2 - NIOCORP DEVELOPMENTS LTDv448164_ex23-2.htm
EX-16.1 - EXHIBIT 16.1 - NIOCORP DEVELOPMENTS LTDv448164_ex16-1.htm
EX-10.6 - EXHIBIT 10.6 - NIOCORP DEVELOPMENTS LTDv448164_ex10-6.htm
EX-10.5 - EXHIBIT 10.5 - NIOCORP DEVELOPMENTS LTDv448164_ex10-5.htm
EX-10.3 - EXHIBIT 10.3 - NIOCORP DEVELOPMENTS LTDv448164_ex10-3.htm
EX-5.1 - EXHIBIT 5.1 - NIOCORP DEVELOPMENTS LTDv448164_ex5-1.htm
S-1 - S-1 - NIOCORP DEVELOPMENTS LTDv448164_s1.htm

 

Exhibit 23.3

 

CONSENT OF LAROCHELLE

 

The undersigned, Eric Larochelle, hereby states as follows:

 

I, Eric Larochelle, assisted with the preparation of the “Amended NI 43-101 Technical Report, Updated Preliminary Economic Assessment, Elk Creek Niobium Project” dated effective August 4, 2015 with an original report date of September 4, 2015 and an amended report date of October 16, 2015 (the “Technical Report”) portions of which are extracted or summarized (the “Summary Material”) in this Registration Statement on Form S-1.

 

I hereby consent to the reference to the Technical Report, the Summary Material and the reference to my name and the names of Roche Ltd. and SMH Process Innovation in the Form S-1 concerning the Technical Report.

 

Date: September 1, 2016 By: /s/ Eric Larochelle
     
  Name: Eric Larochelle, B. Eng.
Title: President, SMH Process Innovation