September 14, 2012

 

Dear Shareholders,

 

Please find below the El Gallo Complex development update.

 

McEwen Mining has completed the construction of El Gallo Phase 1 and commissioning is well under way. The Company expects to pour its first bar of gold over the coming 2 weeks!

 

To view the El Gallo Development Photo Update, please click here.

 

For further information contact:

 

 

 

Jenya Meshcheryakova

Mailing Address

Investor Relations

181 Bay Street Suite 4750

Tel: (647) 258-0395

Toronto, ON M5J 2T3

Toll Free: (866) 441-0690

PO box 792

Fax: (647) 258-0408

E-mail: info@mcewenmining.com

 

 

Facebook: www.facebook.com/McEwenRob

 

Twitter: www.twitter.com/McEwenMining

 

 

If you no longer want to receive announcements from us, please do not reply to this e-mail. Instead simply click here.

 



El Gallo Complex Development Photo Update September 14, 2012

 


Loading heap leach pad 2

 


Leaching underway at the heap leach pad 3

 


Commissioning the carbon columns 4

 


Preparing for blasting inside of the open pit 5

 


Overlooking Samanegio open pit mine 6

 


5.6 million tonnes moved since December 7

 


Backfilling previously mined open pit 8

 


Crushers ramping up to their designed capacity of 3,000 tonnes per day 9

 


McEwen’s Mexican Mining Team! 10

 


 For further information please contact: Jenya Meshcheryakova Investor Relations Tel: (647) 258-0395 x 410 Toll Free: (866) 441-0690 Fax: (647) 258-0408 Email: info@mcewenmining.com www.facebook.com/McEwenRob www.twitter.com/McEwenMining