Investor Presentation
Great Plains Energy
Transource Energy, LLC
Investor Presentation
April 2012
Exhibit No. 99.1
Exhibit No. 99.1
 
 

 
Investor Presentation
Statements made in this presentation that are not based on historical facts are forward-looking, may involve risks and
uncertainties, and are intended to be as of the date when made. Forward-looking statements include, but are not limited to,
the outcome of regulatory proceedings, cost estimates of capital projects and other matters affecting future operations. In
connection with the safe harbor provisions of the Private Securities Litigation Reform Act of 1995, Great Plains Energy and
KCP&L are providing a number of important factors that could cause actual results to differ materially from the provided
forward-looking information. These important factors include: future economic conditions in regional, national and
international markets and their effects on sales, prices and costs, including but not limited to possible further deterioration in
economic conditions and the timing and extent of economic recovery, prices and availability, of electricity in regional and
national wholesale markets; market perception of the energy industry, Great Plains Energy and KCP&L; changes in business
strategy, operations or development plans; effects of current or proposed state and federal legislative and regulatory actions
or developments, including, but not limited to, deregulation, re-regulation and restructuring of the electric utility industry;
decisions of regulators regarding rates the companies can charge for electricity; adverse changes in applicable laws,
regulations, rules, principles or practices governing tax, accounting and environmental matters including, but not limited to,
air and water quality; financial market conditions and performance including, but not limited to, changes in interest rates
and credit spreads and in availability and cost of capital and the effects on nuclear decommissioning trust and pension plan
assets and costs; impairments of long-lived assets or goodwill; credit ratings; inflation rates; effectiveness of risk
management policies and procedures and the ability of counterparties to satisfy their contractual commitments; impact of
terrorist acts, including but not limited to cyber terrorism; ability to carry out marketing and sales plans; weather conditions
including, but not limited to, weather-related damage and their effects on sales, prices and costs; cost, availability, quality
and deliverability of fuel; the inherent uncertainties in estimating the effects of weather, economic conditions and other
factors on customer consumption and financial results; ability to achieve generation goals and the occurrence and duration
of planned and unplanned generation outages; delays in the anticipated in-service dates and cost increases of additional
generation, transmission, distribution or other projects; the inherent risks associated with the ownership and operation of a
nuclear facility including, but not limited to, environmental, health, safety, regulatory and financial risks; workforce risks,
including, but not limited to, increased costs of retirement, health care and other benefits; and other risks and uncertainties.
This list of factors is not all-inclusive because it is not possible to predict all factors. Other risk factors are detailed from time
to time in Great Plains Energy’s and KCP&L’s quarterly reports on Form 10-Q and annual report on Form 10-K filed with the
Securities and Exchange Commission. Each forward-looking statement speaks only as of the date of the particular
statement. Great Plains Energy and KCP&L undertake no obligation to publicly update or revise any forward-looking
statement, whether as a result of new information, future events or otherwise.
Forward-Looking Statement
2
 
 

 
Investor Presentation
 Great Plains Energy (GXP) and American Electric Power (AEP) have formed a joint
 venture, Transource Energy, LLC (Transource), to pursue competitive transmission
 projects
  GXP owns 13.5% through a newly-formed subsidiary (GPE Transmission Holding Company, LLC)
  AEP owns 86.5% through its subsidiary (AEP Transmission Holding Company, LLC)
 
 GXP’s regulated subsidiaries, KCP&L and GMO, will seek regulatory approval to novate
 two Southwest Power Pool (SPP) regional transmission projects they have committed
 to build that are in the initial stages of development
  Sibley-Nebraska City an SPP Priority Project - 345kV, GMO’s share is approximately 170 miles (175
 miles total project), estimated total costs of approximately $380 million, expected in service: 2017
  Iatan-Nashua an SPP Balanced Portfolio Project - 345kV, approximately 30 miles, estimated total
 costs of approximately $54 million, expected in-service: 2015
  KCP&L and GMO to fund 100% of the costs of the two SPP projects until they are novated and will
 be reimbursed by Transource
 Estimated timeframe to obtain Missouri Public Service Commission (MPSC) and Federal
 Energy Regulatory Commission (FERC) approvals to novate the projects is
 approximately 18 months
3
Transource Overview
 
 

 
Investor Presentation
GPE Transmission Holding
Company, LLC
AEP Transmission Holding
Company, LLC
86.5%
13.5%
Transource Ownership Structure
Great Plains Energy Incorporated
American Electric Power
Company, Inc.
100%
100%
Transmission Projects
4
 
 

 
Investor Presentation
 Exclusive vehicle for GXP and AEP to pursue future competitive transmission projects
 throughout the continental United States that fall within the scope of FERC Order 1000
 (regional and inter-regional transmission projects subject to regional cost allocation)
  Initial focus on three regional transmission organizations (RTO) - SPP, Midwest Independent
 Transmission System Operator (MISO) and PJM Interconnection (PJM). Pursuit of new
 transmission in other regions as markets mature
  The venture excludes transmission projects in the Electric Reliability Council of Texas (ERCOT) and
 AEP’s existing transmission project joint ventures
 AEP will operate Transource and provide the majority of staff and services for the
 venture through its service company
  GXP will leverage AEP project execution strengths on the current SPP projects in completing the
 Sibley-Nebraska City and Iatan-Nashua projects
 No earnings impact expected through 2015
  Consistent with GXP stand alone build of two current SPP projects
 Transource funding requirements will be consistent with ownership structure
5
Transource Overview
 
 

 
Investor Presentation
Initial Focus on Three RTOs
6
Southwest Power Pool (SPP)
Midwest Independent Transmission System Operator
(MISO)
PJM Interconnection (PJM)
 
 

 
Investor Presentation
 Long-term growth opportunity through creation of national transmission platform
  Provides opportunity for sustainable, long-term growth in competitive transmission market
  Ability to co-invest in transmission with AEP on a national scale
  First-class partner with largest US transmission system, strong balance sheet and demonstrated
 commitment to transmission growth
  Project execution expertise creates greatest value for customers
  Provides geographic investment diversity
 Diversifies earnings
  Transmission investments help diversify long-term investments
  Enhances returns on future capital investments by way of FERC’s regulatory construct for
 transmission
  Improves ability to earn authorized ROE
 Enhances financial flexibility
  Reduces medium-term capital expenditure requirements and external financing needs
  Smoothes capital requirements with near-term environmental investments and longer term
 transmission opportunities
  Reduces regulatory lag due to FERC cost recovery mechanisms
7
GXP Joint Venture Benefits
 
 

 
Investor Presentation
GXP Projected Capital Expenditures*
SPP $4.2
8
*Projected capital expenditure excludes Allowance for Funds Used During Construction (AFUDC)
 
 

 
Investor Presentation
State authority for Transource to build transmission will be required, and other
state approvals may be asserted
State Regulatory Process
 Obtain a line certificate for Transource to build transmission in Missouri
  A line certificate, providing utility status specific to proposed line, will be requested prior to
 constructing electric transmission facilities in Missouri
  Transource anticipates making the necessary filing with the MPSC this summer
 Novate current KCP&L and GMO projects to Transource
  KCP&L and GMO anticipate making the necessary filings with the MPSC this summer
 KCP&L and GMO will request waivers of Missouri Affiliate Transaction Rules
  MPSC affiliate transaction rules may apply as ownership in Transource is greater than 10%
  Missouri affiliate transaction rules are asymmetrical and require utilities to pay lesser of cost or market to
 affiliates and receive greater of cost or market from affiliates
 Anticipate working through state filings in approximately one-year however, there is
 no statutory time period in which the MPSC must act
9
Regulatory Process
 
 

 
Investor Presentation
FERC must approve the novation to Transource as well as establish formula
rates and incentives
Federal Regulatory Process
 Transource will request FERC approval of formula rates (which may include certain incentive
 components)
  Typically, FERC formula rate cases are settlement cases and are completed in 10 to 12 months
  Transource will request FERC approval for certain incentives for the projects
  Incentives may include: CWIP in rate base; recovery of abandoned plant, various ROE adders and proposed
 hypothetical capital structures
 FERC approval of SPP’s novation of GXP projects to Transource
  SPP files novation agreement for approval by FERC
  Transource must meet several SPP criteria to receive novation including: creditworthiness; a signed SPP
 membership agreement; and demonstrated technical, financial and managerial qualifications
10
Regulatory Process
 
 

 
Investor Presentation
Novation
Agreement
SPP
Novation
Incentive Rate and Formula Rate Approval Process
Novate Existing GXP Projects Approval Process
Line Certificate Approval Process
Estimated Regulatory Approval Timeline
11
2012
2013
Q2
Q3
Q4
Q2
Q3
Q4
Q1
Applications
Filed at
MPSC
(Jun-12)
MPSC
Approvals
(Aug-13)
Application
Filed at FERC
(Jun-12)
FERC
Approval of
Rates
(May-13)
Begin
SPP Novation
Process
(Jun-13)
SPP Board
Approval
(Aug-13)
FERC Novation
Acceptance
(Dec-13)
Novation
Agreement
Filed at FERC
(Oct-13)
MPSC approval
FERC approval
SPP process
MPSC
Approval
Process
FERC
Approval
Process
Novation
Process
Goal is to complete novation of the SPP projects as soon as possible