Attached files

file filename
S-1/A - FORM S-1/A - Armstrong Resource Partners, L.P.c65698a3sv1za.htm
EX-10.9 - EX-10.9 - Armstrong Resource Partners, L.P.c65698a3exv10w9.htm
EX-23.3 - EX-23.3 - Armstrong Resource Partners, L.P.c65698a3exv23w3.htm
EX-23.2 - EX-23.2 - Armstrong Resource Partners, L.P.c65698a3exv23w2.htm
EX-10.8 - EX-10.8 - Armstrong Resource Partners, L.P.c65698a3exv10w8.htm
EX-10.10 - EX-10.10 - Armstrong Resource Partners, L.P.c65698a3exv10w10.htm
EX-10.14 - EX-10.14 - Armstrong Resource Partners, L.P.c65698a3exv10w14.htm
EX-10.15 - EX-10.15 - Armstrong Resource Partners, L.P.c65698a3exv10w15.htm
EX-10.13 - EX-10.13 - Armstrong Resource Partners, L.P.c65698a3exv10w13.htm
EX-10.12 - EX-10.12 - Armstrong Resource Partners, L.P.c65698a3exv10w12.htm
EX-10.16 - EX-10.16 - Armstrong Resource Partners, L.P.c65698a3exv10w16.htm
EX-10.39 - EX-10.39 - Armstrong Resource Partners, L.P.c65698a3exv10w39.htm
EX-10.51 - EX-10.51 - Armstrong Resource Partners, L.P.c65698a3exv10w51.htm
EX-10.34 - EX-10.34 - Armstrong Resource Partners, L.P.c65698a3exv10w34.htm
EX-10.27 - EX-10.27 - Armstrong Resource Partners, L.P.c65698a3exv10w27.htm
Exhibit 10.11
TENNESSEE VALLEY AUTHORITY
COAL ACQUISITION & SUPPLY

1101 Market Street, MR 2A
Chattanooga, Tennessee 37402-2801
CONTRACT SUPPLEMENT
         
TO: Armstrong Coal Company Inc
  Supplement No.    4
       7701 Forsyth Boulevard 10th Floor
  Date    December 11, 2008
       St. Louis MO 63105
  Group No.    612
 
  Contract No.    40668
 
  Plant    Various
 
  Name of Mine    Big Run
Attention Mr. Martin Wilson
Per the Contract Section 10.1 the Base Price will be adjusted by 2.75% January 1, 2009. The new base price shall be $30.753 per ton
cc: Tate Rich, President
Delta Coals,LLC
95 White Bridge Road #404
Nashville Tennessee 37205
         
  Tennessee Valley Authority
 
 
  By   /s/ Eddie Spicer    
    Eddie Spicer   
    Fuel Contract Administrator   
 
 
  /s/  
  Contract Support Specialist  
 
 
  /s/  
  Manager of Coal Supply

Date 1-7-09