Attached files

file filename
EX-32.1 - EXHIBIT 32.1 - CBAK Energy Technology, Inc.exhibit32-1.htm
EX-99.4 - EXHIBIT 99.4 - CBAK Energy Technology, Inc.exhibit99-4.htm
EX-99.9 - EXHIBIT 99.9 - CBAK Energy Technology, Inc.exhibit99-9.htm
EX-31.2 - EXHIBIT 31.2 - CBAK Energy Technology, Inc.exhibit31-2.htm
EX-99.2 - EXHIBIT 99.2 - CBAK Energy Technology, Inc.exhibit99-2.htm
EX-99.3 - EXHIBIT 99.3 - CBAK Energy Technology, Inc.exhibit99-3.htm
EX-99.6 - EXHIBIT 99.6 - CBAK Energy Technology, Inc.exhibit99-6.htm
EX-31.1 - EXHIBIT 31.1 - CBAK Energy Technology, Inc.exhibit31-1.htm
EX-99.5 - EXHIBIT 99.5 - CBAK Energy Technology, Inc.exhibit99-5.htm
EX-99.1 - EXHIBIT 99.1 - CBAK Energy Technology, Inc.exhibit99-1.htm
EX-99.7 - EXHIBIT 99.7 - CBAK Energy Technology, Inc.exhibit99-7.htm
EX-99.13 - EXHIBIT 99.13 - CBAK Energy Technology, Inc.exhibit99-13.htm
EX-99.12 - EXHIBIT 99.12 - CBAK Energy Technology, Inc.exhibit99-12.htm
EX-99.10 - EXHIBIT 99.10 - CBAK Energy Technology, Inc.exhibit99-10.htm
EX-99.11 - EXHIBIT 99.11 - CBAK Energy Technology, Inc.exhibit99-11.htm
EX-99.14 - EXHIBIT 99.14 - CBAK Energy Technology, Inc.exhibit99-14.htm
10-Q - FORM 10-Q - CBAK Energy Technology, Inc.form10q.htm
EX-32.2 - EXHIBIT 32.2 - CBAK Energy Technology, Inc.exhibit32-2.htm

Summary of Loan Agreement Entered into by and between Shenzhen BAK Battery Co., Ltd. (“the Company”) and Shenzhen Eastern Branch, Agricultural Bank of China (“the Creditor”) Dated April 13, 2011

Main contents

  •  
  • Contract number: 81010120110000280;

       
  •  
  • Loan principal: RMB 60 million;

       
  •  
  • Loan term: from April 13, 2011 to April 13, 2012;

       
  •  
  • Floating interest rate: Interest rate of loan shall be equal to the benchmark rate announced by the People’s Bank of China, and be adjusted every one month;

       
  •  
  • Interest accrued and settled per month, interest settlement day is the 20th day of each month;

       
  •  
  • Penalty interest rate for delayed repayment: current interest rate plus 50% * current interest rate;

       
  •  
  • Penalty interest rate for embezzlement of loan proceeds: current interest rate *1;

       
  •  
  • Purpose of the loan is to provide working capital for loan payment of the Company;

       
  •  
  • Advanced repayment of loan needs to be approved by the Creditor;

       
  •  
  • Breach of contract penalties: correct the breach of contract in time limit; suspension of loan unprovided; release loan agreement, demand prepayment of loan principal and interest before maturity; imposition of punitive interest incurred due to delayed loan; imposition of punitive interest for embezzlement of loan; imposition of plural interest for unpaid interest; withdraw from any accounts of the Company the loan principal, interest and other fees; compensation for the Creditor’s expenses incurred due to demanding the loan principal and interest in case of litigation, etc.

    Headlines of the articles omitted:

    • Termination and explanation

    • Undertaking of the Company

    • Loan arrangement

    • Interest clearing of the loan

    • Payment of the loan

    • Rights and obligation

    • Interest penalty of loan

    • Guarantee of the loan agreement

    • Disputation settlement

    • Validity

    • Text