Exhibit 10.27
SCOPE OF WORK: n/a CAF NO.: 001 DATE: Feb. 28, 2011
P.O. NO.: DESCRIPTION: SELLER:
P.O. # E-00010 Moly033.01 Circuit & Phase 2 Mixers Quinn Process Equipment Co.
PROCUREMENT: 1) COMPLETE SUMMARY OF CHANGE 2) ATTACH BACKUP DOCUMENTATION 3) FORWARD CAF TO PROJ. ENGINEERING
SUMMARY OF CHANGE: 1) Addition of secondary circuit mixers. 2) Revising circuit design.
COST IMPACT SCHEDULE IMPACT
ORIGINAL P.O. AMOUNT: $21,437,853.00 SCHEDULE EXTENSION: wks.
TOTAL PREVIOUS CHANGES: $0.00 SCHEDULE REDUCTION: wks.
AMOUNT THIS CAF: $4,553,920.00 NEW P.O. COMPLETION DATE: Oct 2, 2012
REVISED P.O. AMOUNT: $25,991,773.00
(THE CHANGES IN THIS CAF WILL BE INCORPORATED INTO P.O. CHANGE ORDER NO.: 001 )
BUYER: /s/ Charlet Davis DATE: Feb. 28, 2011
ENGINEERING: 1) COMPLETE DESCRIPTION AND REASON FOR CHANGE 2) FORWARD CAF TO PROJECT CONTROLS
DESCRIPTION AND REASON FOR CHANGE: Addition of Phase 2 mixers.
Y N
TECHNICAL CHANGES APPROVED: x
REVISED EPR TO BE ISSUED:
PROJECT CONTROLS: 1) ADD BUDGET INFORMATION 2) FORWARD CAF TO PROJECT MANAGER
BUDGET CHANGE THIS CAF FORECAST FINAL VARIANCE commited to date REASON FOR VARIANCE
COMMENTS: n/a
COST CODE n/a PROJECT CONTROLS n/a DATE: n/a
/s/ Marc Privitera 2/28/11 /s/ Samar Adranly 2/28/11
PROJECT ENGINEER DATE PROJECT CONTROLS MANAGER, SAMAR ADRANLY
/s/ Todd Hancock
DATE
2/28/11
/s/ Charlet Davis
2/28/11
PROJECT PROCUREMENT MANAGER, CHARLET DAVIS
/s/ John Burba DATE
2/28/11 PROGRAM MANAGER, TODD HANCOCK
/s/ Brock OKelley DATE
2/28/11
MOLYCORP, DR. JOHN BURBA DATE MOLYCORP, BROCK OKELLEY DATE
RETURN COMPLETED FORM TO PROCUREMENT TO COMMIT AWARD |